Process connection of compressor unit skid with liquid ring

PROJECT DESCRIPTION

PROCESS CONNECTION OF COMPRESSOR UNIT SKID WITH LIQUID RING


MONTER – STROJARSKE MONTAŽE d.d. Carried out the procurement of materials, its prefabrication and the production of pipelines for the interconnection of the rolling unit of the liquid ring compressor unit for Investor GARO SpA, owned by Gardner Denver.

Skid units consist of the following elements:

1. Two liquid-driven compressors,
2. Separator
2. Two air coolers, and
4. manual, automatic and safety valves.
During the execution of the work, a test dimensional assembly, pressure test of all pipe lines and their anticorrosive protection were performed.

After the final assembly, supervised by the Investor and the end user INA – Oil Industry d.d., the unit components have been dismantled and transported to the site of installation at the Rijeka Oil Refinery.

  • Clean and modern architecture
  • Eco friendly materials
  • Idea to final solution